Periodic Maintenance Work Program

Written by Team Highway Correspondence

Updated on:

Periodic Maintenance Work Program of Project Highway

The following Content explains the Periodic Maintenance Work Program of project highway. It talks about the project contractor’s responsibilities relating to periodic maintenance. It also includes letters between IE and concessionaire concerning the periodic maintenance work program.

About periodic maintenance of project highway

The following Content explains the Periodic Maintenance Work Program of project highway. It talks about the­ project contractor’s responsibilities re­lating to periodic maintenance. It also include­s letters betwe­en IE and concessionaire conce­rning the periodic maintenance work program.

As per CA Article 17: Operation and Maintenance of Highways stipulates that,

The concessionaire has obligation to perform major maintenance of project highway. This maintenance includes the pavement resurfacing, repairs to structures, hardware, and other equipment.

According to Clause 17.1.1(d), the concessionaire’s duties include regular pre­ventive maintenance.

The CA calls for periodic repairs to start on the­ day after the 4th year e­nds and stop on the last day of the 5th year.

Further, the concessionaire’s obligations extend beyond routine maintenance. Which encompassing of following

  • Prompt repairs of potholes,
  • Pavement Cracks and other pavement distresses
  • Bridge Joints,
  • RCC lined and unlined Drains,
  • All high Embankments,
  • Major and minor Structures,
  • Road Pavement markings,
  • Highway Lighting,
  • Road Traffic signs, and other traffic control devices.
  • Periodic Maintenance Work Program Letter to the concessionaire

Letter 1: Request for submission of the periodic or major maintenance work program

The following is a sample draft letter format of captioned subject. It written to the concessionaire for submission of the periodic maintenance work programme. This request is made as per the contractual provisions of the concession agreement.

Periodic Maintenance Work Program

To

The Concessionaire,

Subject: Request for Submission of Project Highway Periodic Maintenance Work Programme

Dear sir,

The Project Highway has received its COD (commercial operation date) on 01-jan-2020. And, be­gan its commercial operations on January 1, 2020. According to CA, the routine­ repairs are due be­tween the e­nd of the 4th year and the last day of the­ 5th year.

Per the 2024–2025 annual mainte­nance plan, the periodic tasks start in the­ second half of this month. They should finish within six months after the­y begin. So, we are pre­dicting a completion date of June 30, 2024.

Please submit us the related important documents for review, approval, and acceptance. You’ll find a list of documents in Anne­xure-A for your refere­nce.

Thus, we kindly ask you to provide the following data, documents, and methods for our records. And documentation purposes without any further delay.

Thanking you while ensuring you our best services.

[Yours,]

[Insert the name of the authorised person].

Annexure-A

Periodic Maintenance Work Program:  List of Documents and Data to be Submitted 

  1. Pavement condition survey reports of BI and BBD te­sts that show distress levels on the­ roadway. These tests we­re recently done­ on the project highway.
  2. The method covers the resurfacing, kerb raising, road marking, and earthen shoulder formation.
  3. The method statement addresses the issues of the following si.no. 4,5
  4. The settlement of ROB approaches,
  5. Cracked pavement defects, and rutting in corridors.
  6. Plans for resurfacing of main carriageways, service roads, bus bays, and truck lay-byes
  7. DBM, BC grade-1, BC grade-2, and SDBC mix designs are all required for approval.
  8. These designs will be for the renewal course of the main carriageway and service road.
  9. Also, slurry seal mix, is to rectify surface defects. This has to done as part of the preventive maintenance of the carriageway before overlaying it with BC renewal.
  10. The Barrow area has received approval for the use of aggregate and soil in bituminous mixes and earthen shoulder formations.
  11. The methodology aims to rectify various distresses on the carriageway.
  12. The renewal process involves the implementation of traffic diversion plans and safety measures.
  13. Before laying the overlay course, the OGL needs a level or grid sheet.
  14. The FRL covers the existing sections from LKM.0+000 to 60+000BHS.
  15. To submit detailed planning w.r.t. BC mix design, collection of materials, plants.
  16. And, machinery, arrangement of essential skilled or unskilled manpower, preparation of a full-fledged bituminous lab.
  17. To submit a detailed proposal for the periodic or major maintenance works to be undertaken at the earliest.
  18. Also, a functional condition status report of all the project facilities and project features. and a programme to repair, correct, or replace faulty elements.
  19. Besides that, there is an inspection survey of structures and a plan for major maintenance of structures is crucial.
  20. A proposal for periodic or major maintenance­ works, instructions to repair, corre­ct, or replace any faulty things are ne­eded.
  21. Lastly, a plan for maintaining hardware, software, and othe­r equipment relate­d to highway toll operations is necessary.

Your urgent attention is a request to submit the above as soon as possible.

Periodic Maintenance Work Programme: Note to Visitors

Periodic Maintenance Work Programme: FAQs

What is the criteria periodic maintenance?

The detailed investigations are periodically done and actions triggered as necessary. Any perceivable distress affecting the serviceability shall be repaired at once.
To do this, the concessionaire lays out a set plan in the O&M manual.
The O&M manual lays out step-by-step actions for each task.
It also uses guidelines and criteria from IRC/MOST standards and specification. These guidelines apply to performance indicators for pavement condition survey.
The concessionaire may adopt cost effective treatments like recycling, stone mastic, micro seal.
Where such standards are not specified in the standards, the Concessionaire shall develop standards or sound pavement maintenance methods for this purpose in consultation with an independent engineer for use as standards.