Letter on proposal for change of DBM Crust thickness
Content Brief:
- Letter on proposal for change or modification of DBM Crust thickness: This content pertains to the review observations on the proposal to change the specifications of the bituminous components of DBM and BC. And offer comments upon the concessionaire’s proposal by the independent engineer.
- These observations of IE are followed by the concessionaire’s submission. And intimate the concessionaire through a letter of IE’s findings and observations.
- The following content includes an approval or denial of permits with site, financial, environmental, and legal-specific reviews, terms, and conditions.
- This content also includes the pavement composition for new construction/reconstruction/realignment as per CA.
CA provisions regard Pavement composition for new construction/reconstruction/realignment.
- As per CA Schedule B, Development of the Project Highway, the pavement composition for new construction/reconstruction/realignment is as follows:.
- The pavement composition shall be designed as per IRC: 37 and for a life of 15 years. The minimum composition of the new flexible pavement shall be as shown in Table B-3 below, which is based on the subgrade CBR value (4-day soaked value) at 97% modified Proctor density.
- The indicated pavement composition is for the purpose of guidance alone. Any additional thickness in the design over that indicated in the bidding documents shall not constitute a change in scope of work nor qualify for a variation order.
- Table B-3: Composition of new flexible pavement for main carriageway
Chainage Design Traffic (MSA) Proposed Pavement Thickness (mm) Remarks From To Wearing course BC (mm) Binder course DBM (mm) Granular base WMM (mm)
Granular Sub-base GSB (mm)
Total (mm) 00.000 10.000 65 40 125 250 200 615 New Construction 10.000 20.000 55 40 120 250 200 610 Reconstruction 20.000 30.000 35 40 105 250 200 595 Realignment 40.000 60.000 25 40 100 250 200 590 Bypass
- Table B-4: Composition of new flexible pavement for main carriageway
Chainage | Proposed Pavement Thickness (mm) | Remarks | ||
From | To | Wearing course BC (mm) | Binder course DBM (mm) | |
30.000 | 40.000 | 40 | 105 | Overlay portion |
Letter on proposal for change of DBM Crust thickness
To
The Concessionaire Subject: Proposal for change or modification of DBM works of the project highway-regDear Sir, In connection with the proposal for changing the specifications of the following bituminous components as proposed in the agreement tables B-3 and B-4 as highlighted above. i.e. From km. 20+000 to km. 30+000 As per CA table B-4, new pavement. And,From km. 30+000 to 40+000 as per CA table B-4 Overlay thickness. Proposal by the Concessionaire:-
(Based on the improved subgrade CBR (10%) in comparison to the designed subgrade CBR (8%)) We have completed our review and have no objection to allowing you to follow the new proposed composition based on the following terms and conditions.
Moreover, it is allowing you to follow the new proposed composition as cited upon the above conditions without any financial implications to the highway authority. These are for your information and necessary actions. |
A note to the visitor about the letter on proposal for change of DBM Crust thickness
Please note that the concession agreement for the DBFOT project under the PPP mode serves as an example of the aforementioned contractual conditions. For the period 2016–2018,
Afterwards, make sure to make the necessary modifications to the existing contractual conditions. Write a letter that aligns with the concession agreement applicable to the particular project.
It is that a few important and mandatory aspects are only discussed herewith. Kindly note that the above Letter on Proposal for Modification of DBM Crust Thickness are considered examples. You may adopt the gist of the subject and change it to suit the current need. And before using this content in your letter draughting, you need to ensure the specific material, other aspects, etc.
Also read the reconstruction methods of carriageway and the site instruction letter notice on various issues of ongoing DBM construction works:
You can find various sample draft formats for highway construction phase, operation, and maintenance correspondence.
Letter on proposal for change of DBM Crust thickness: FAQ’s
The team highway correspondence will update relevant FAQs based on the quarries as and when requested by the visitors.