Site Instruction on DBM Works
Content brief:
-
The following content pertains to the highway project construction works.
-
It contains the independent engineer’s findings of defective, inaccurate, and substandard DBM works on the project highway. These are with particular reference to specifications and standards as specified in CA.
-
This includes a letter of notice to the concessionaire by the IE about the issues on the subject. I.e., on-going, completed and balance or future dense bituminous Macadam construction works.
-
It refers to defects identified in dense bituminous macadam construction during site inspection by an independent engineering team.
-
These letter notices summarise the various instances of improper DBM construction works on the project highway.
-
These site instructions are in a fashion that summarises the identified defect. And prescribing remedial measures along with a time frame for corrective actions by an independent engineer.
-
Also, it provides comprehensive details of various issues along with a photographic presentation.
Site instruction on DBM works
The following is a sample site instruction note on faulty DBM construction works on highway construction.
Case-1: Site instruction letter notice on completed and future DBM construction works-reg.
To The Concessionaire Subject: About completed and balance or future dense bituminous Macadam construction works-Reg. Dear Sir, You have completed a significant length of DBM construction work in some portion of the project highway. But you have failed to comply with the following points:
So, you are being instructed to comply with the points raised in this letter. Thanking you. |
Case-2: Site instruction letter notice on various issues of On-going DBM Construction works-reg.
To The Concessionaire Subject: About On-going Dense Bituminous Macadam Construction Works-Reg. Reference: As above Dear Sir, Issue:1 Non-compliance with site verbal instructions of Independent Engineer:
Issue:2 Non-raising of RFI’s by the contractor/Concessionaire
Issue:3 Inadequate arrangements of tools and machinery at the work site
Issue:4 Improper surface preparation and priming application
Issue:5 Non-standard Construction jointsThe qualities of the joints between consecutive patches are much below the standard; hence, you are being instructed to improve the joints to the desired level. Issue:6 Unsatisfactory/Poor Surface finishingDuring the TL of IE’s visit of the site on 22/08/2024, it was found that lots of segregations are there in the DBM layer constructed on 20/08/2014, for the chainage 14.500 to 14.890. On detailed scrutiny, it was decided by the IE that the DBM laid within the chainage 14.875 to 14.890 is to be removed, relayed, and recombined with immediate effect. You are being instructed to comply with the same. Issue:7 Site-level quality control testsIt has been observed that in the cases of completed DBM layers, neither the cores are being taken as per the frequencies nor in the presence of IE’s representatives. Please rectify your modus operandi. Issue:8 About the riding quality of the DBMDuring the visit of the Project Highway on 08/08/2024, the Highway authority expressed his deep concern about the riding quality of the DBM in section 4. So, you are being instructed to improve the surface regularities to the desired level, with immediate effect. Issue:9 Other & miscellaneous workDuring the visit of the Project Highway by the T.L. of IE, it has been found that the kerb heights for the LHS and RHS of the same patch for chainages 18.000 to 18.500 are not the same. You are being instructed to rectify the same and ensure that it does not recur in the future. All these are for immediate compliance only. Thanking you, |
Case-3: Site instruction letter notice on serious discrepancies in On-going DBM Construction works-reg.
Case-1 To The Concessionaire Subject: DBM works-Section 3- Reg Dear Sir, It has been observed that, you have just started the DBM work in package III of the Project Highway, with following serious discrepancies:-
So, under the above circumstances, we would like to intimate you that, we are not in a position to accept unauthorized modifications of Concession Agreement Provisions, hence, you are being instructed to stop the unauthorized DBM construction works with immediate effect, else you will be responsible for the adverse consequences. Thanking you. Case-2 To The Concessionaire Subject: Deficiencies in DBM Construction works- Reg. Dear Sir, During our team’s recent site visits, we have found following deficiencies:- 1. The DBM over lay was completed in the following chainages without submitting the existing bituminous road top levels to finalize the ultimate overlay thickness.
2. The Overlay works were completed from Ch 15+060 to Ch16+100, without construction of Krebs. 3. You have laid the kerb on existing bituminous road from Ch15+010 to Ch 15+920 LHS, which are not being executed as per drawings submitted by you. 4. Kerb lying was completed from Ch 14+020 to Ch 14+250 BHS, but not are in alignment and top levels are not matching. Hence, you are being instructed to improve your workmanship and rectify the deficiencies. With immediate effect. Thanking you, |
Case-4: Site instruction Letter notice on Undulations and settlement observed on DBM surface-reg.
To
The concessionaire Subject: – Undulations and settlement observed on DBM surface Dear Sir, Please refer to the site visit of the under signed on 1st September 2024. The undulations and settlement were observed at following locations of the Newly Constructed Road at the following Chainages. 1) Ch.05+000 to Ch.05+900 2) Ch.06+550 to Ch.10+350 3) Ch.10+560 to Ch.11+400 We have previously brought to your notice that Wet Mix Macadam is laid directly on the existing/erst-while bituminous surface at these portions. The existing/former bituminous surface in the median areas is not removed which created drainage problem in the median resulting in undulation and settlement on pavement surface. Thus, the existing road to be reconstructed at cited locations based on our pavement Engineer site visit/site observations. Further, (After attending the notified defect i.e. rectification by reconstruction)to submit reconstructed DBM top surface levels/ surface regularity results of these locations for our review. Thanking you |
Note to a visitor about the Site instruction on DBM works
It is that a few important and mandatory aspects are only discussed herewith. Kindly note that the above inspection observations are considered examples. You may adopt the gist of the subject and change it to suit the current need. And before using this content in your letter drafting, you need to ensure the specific CA Contractual conditions and other aspects, etc.
It is suggested to read article about Site instruction on faulty embankment construction on Highway project
Also, read about the highway Improper bituminous construction works and traffic diversion plans on the highway.
Additionally, you can find various sample draft formats for highway operation and maintenance correspondence.