Site instruction on earthen shoulder

Written by Team Highway Correspondence

Updated on:

Site instruction on earthen shoulder construction and maintenance

  • The following content pertains to the highway project site instruction earthen shoulder construction and maintenance works.

  • It contains IE’s remarks on earthen shoulder construction works on project highway.

  • This article includes a sample instruction notice to the concessionaire by the IE about the earthen shoulders.

  • It reference the defects identified in earthen shoulder construction at construction phase of highway. Such as poor construction and non construction of shoulder as per road construction sequence.

  • It also refers to deficiencies identified in earthen shoulder maintenance during the operation phase of the highway. Such as poor maintenance and damaged conditions.

  • These instructions contains the method that captures the detected error. Also, prescribing remedial measures along with a time frame for corrective actions by an independent engineer.

Construction Phase: Sample site instructions on construction of earthen shoulder in various conditions and contexts

Case-1 Subject: Site instruction on Non-construction of earthen shoulder

To

The concessionaire

Subject: Non Construction of earthen shoulders etc.,-Reg.

Site instruction on earthen shoulder

Dear Sir,

In spite of our several instructions, we have found that the construction of earthen shoulders, either before or along with the corresponding crust layers, is not being done.

Very recently it has been found in section II, that, WMM work is in progress without any shoulder construction, which is faulty as:

The shoulder provides the necessary lateral support while compacting the corresponding crust layer.

Post construction of shoulder, do not guarantee the achievement of desired level of compaction. Hence chances of rain cuts in the shoulder remains.

Under the above circumstances, you are once again being instructed to undertake the shoulder construction before taking up the corresponding crust layer only.

Thanking You,

Case-2 subject: Site instruction on Poor Construction of earthen shoulders

To

The concessionaire

Subject: Poor Shoulder construction works

Site instruction on earthen shoulder

Dear Sir,

In spite of our strong objections for the methods applied in WMM constructions in some part of the Project Highway, you are continuing the same procedures. Following are the points:

During our teams recent visits, we have found, that as usual the earthen shoulder being constructed only after the completion of 2nd layer of WMM works at number of places.

Which mean you are constructing an earth work with a thickness of 250 mm. Which violates the provision of MORT&H vide clause 305.3.5.1, and without any lateral support, WMM are being compacted

So, once again we are instructing to stop the faulty practices with immediate effect.

This is for immediate compliances only.

Thanking you

Case -3 subject: Site instruction on Non construction of earthen shoulders due to LA issues.

To

The concessionaire

Subject: Non construction of earthen shoulders due to LA issues

Dear Sir,

At km.45+150 service road the carriageway features are built not to the standards. Here earthen shoulder is yet to be constructed. The edge of the road shall be adequately shielded with barricade subject to traffic safety until that location constructed to approve GFC drawings.

This is for immediate compliances only.

Thanking you

Maintenance phase: Sample instructions on earthen shoulder maintenance at various circumstances and conditions

Case -4 subject:

Site instruction on Non maintenance of of earthen shoulders to intact conditions

To

The concessionaire

Subject: Abruptly deformed embankment slope and earthen shoulder

Dear Sir,

During the regular site inspection it is observed that Abruptly deformed embankment slope and earthen shoulder from km.25+100 to 27+500.

To maintain the carriageway and its associated elements in conformity with good industry practices. To be undertake the rectification and restoration of the abruptly deformed /lost width of the embankment slope and earthen shoulder to the standard width.

It is to instruct that to maintain the earthen shoulders on project highway intact under operational condition capable of adequately performing its function at all times and in all weather conditions.

This is for immediate compliances only.

Thanking you

Case -5 subject: Site instruction on Foreign material and water stagnations on earthen shoulders.

To

The concessionaire

Subject: Need of earthen shoulder maintenance

Dear Sir,

During the monthly site inspection of IE it is observed that, foreign material and water stagnations on earthen shoulder. All the foreign material upon the earthen shoulder and ROW shall be removed and the earthen shoulder to maintain for clean, orderly condition to the level of the carriageway. And shall maintain in a trafficable condition at all times.

Shall submit a compliance report with in the time limes as specified in CA subject to particular.

Thanking you

Note to a visitor about the Site instruction on earthen shoulder construction and maintenance.

It is that a few important and mandatory aspects are only discussed herewith. Kindly note that the above inspection observations are considered examples. You may adopt the gist of the subject and change it to suit the current need. And before using this content in your letter drafting, you need to ensure the specific CA Contractual conditions and other aspects, etc.

It is suggested to read the article about site instruction on faulty highway embankment construction.

Also, read about the highway Improper bituminous construction works and traffic diversion plans on the highway.

Additionally, you can find various sample draft formats for highway operation and maintenance correspondence.

FAQ’s related to Site instruction on earthen shoulder construction and maintenance.

The team highway correspondence will update soon.