Site instruction letter on structure works
Content brief:
- The following content pertains to the highway project structure construction works.
- It contain a independent engineer’s findings of defective bridge, underpass and other civil structural construction works on project highway.
- This article includes a various sample site instruction notices or letters to the concessionaire by the IE.
- It reference to defects identified in structure construction during site inspection by independent engineer team.
- These site instructions are in a fashion of summarizes the identified defect. And, prescribing remedial measures along with a time frame for corrective actions by an independent engineer.
- The following are the various sample site instruction letters on structure construction works
Site instruction letters on structure works
Letter on bridge superstructure wearing course
To
The concessionaire Subject: DBM laying over the Deck Slab of Minor Bridge Km 18+525-reg Dear Sir, With reference to subject location, without completion of Bridge miscellaneous items like Drainage spouts, Buried type expansion joints and mastic asphalt layer, you have carried out the laying of DBM over the widened Deck Slab. This is not advisable and good industry practice for quality assurance to lay DBM as wearing course instead of BC over the Bridge Deck and before laying wearing course over the bridge deck complete all the specified miscellaneous items i.e. Drainage spouts, Buried type expansion joints and 25mm thick mastic asphalt layers. This is for your information and compliance please Thanking you |
Letter on slow and dead progress in structure works
To
The Concessionaire Subject: Slow Progress of vehicular underpass structures. Dear Sir. We noticed during our recent site visits that you have not started the construction of The VUP/LVUP’s structures at site as on date at following chainages Ch.13+600 Ch.35+200, Ch.47+800 and Ch.53+360 You are unable to start the work due to shortage of agencies/manpower/shuttering plates. As you aware it may take long time to complete the retaining walls and these balance 4 Nos VUP/LVUP structures in the village limits which is affecting approx 13 km length of road. Also, 6 no of VUP’s are currently under progress upon the project highway at isolated locations. These structures progress are not up to the mark. It is that the progress of these structures are dead slow in terms of project milestons and project completion schedules of CA. As per discussions with you at our office today, we are not agreeing with your contention that the work was stopped by the local public at all villages. Concessionaire has to mobilize the resources at site /start the works immediately to complete the project on schedule time. These are for your attention and immediate Compliances Thanking You, |
A Note to the Visitor on the Site instruction letter on structure works
Please note that the concession agreement for the DBFOT project under the PPP mode serves as an example of the afore-mentioned contractual conditions. For the period 2016–2018,
Afterwards, make sure to make the necessary modifications to the existing contractual conditions. Write a letter that aligns with the concession agreement applicable to the particular project.
It is that a few important and mandatory aspects are only discussed herewith. Kindly note that the above inspection observations are considered examples. You may adopt the gist of the subject and change it to suit the current need. And before using this content in your letter drafting, you need to ensure the specific CA contractual conditions and other aspects, etc.
Also Read the site Instruction on DBM work.
Site Instruction on earthen shoulder
You can find various sample draft formats for highway operation and maintenance.
Additionally, you can find various sample draft formats for highway construction.
FAQ’s related to Site instruction letter on structure works
The team’s highway correspondence will update relevant FAQs shortly.